Construction Timeline

Timeline for construction project

Stay Informed

Sign up for the Park & Rec E-News to keep up-to-date on the project. Be sure to select "Parks & Recreation News."

About the Project

Construction began in April 2016 on a new Shakopee Ice Arena and improvements to the existing Community Center. The completed project will include: 

  • Two NHL-sized rinks, locker rooms, dryland space, meeting rooms, concessions area
  • New 24,000-square-foot aquatic center with water slide, zero-depth-entry pool, four-lane lap pool, locker rooms, sauna
  • Dedicated senior lounge
  • Engima Teen Center
  • New fitness center, two aerobics studios, spinning studio
  • Indoor playground
  • Drop-in child care
  • Community Room available for community rentals
  • Four multi-purpose and small meeting rooms for community rentals

Updates

Friday, Feb. 3 Update: Phase 5 of the Community Center renovations is in full swing. If you drive past the Community Center you will notice that the southwest corner of the building is gone. This area will be bumped out and replaced with windows to let sunlight into the new pool. A temporary wall will be built in this corner in the next few weeks so that the new walls can be constructed out of the elements.

Crane removing building wall

The new interior load bearing walls are currently under construction and will be completed by Feb. 10. The new floors of the future fitness area and aerobic rooms will be set the week of Feb. 12. The pool area and locker rooms are also taking shape! The plan is to dig the zero depth pool the week of Feb. 20.

Crews adding walls in former ice arena space

See photos of construction progress


The temporary fitness center is located in the future indoor playground space. Enigma Teen Center is closed through the duration of the project (through June 2017).

 About the Project

The city is undergoing a $30.4 million recreation improvement project (Option A [PDF]) that includes construction of:

  • New two-sheet, off-site ice arena
  • Community Center remodeling, including expanded fitness, senior lounge, indoor playground and child care
  • Aquatic facility in the existing ice arena shell

Construction began in April 2016 with completion of the ice arena scheduled for December 2016. Community Center renovations are projected to wrap up by June 2017.

Final design

292 Design Group designed the new Ice Arena and Community Center improvements:

Financing

In December 2015, the City Council awarded contracts to 24 bidders for $25,826,178. See a full list of the contract awards. Additional fees, including design, sewer and water charges, security measures and owner's costs, bring the full cost of the project to $30,416,779.

  • Shakopee Ice Arena and Community Center Estimate [PDF]: The first table includes construction costs, including those approved through the contract bid process. The second table includes owner's costs, such as furniture, fixtures and equipment. Note, some costs are estimates/allowances identified by the design team. The contingency fund is for possible unforeseen expenses.

In December, the City Council also awarded the sale of 20-year general obligation tax abatement bonds in the amount of $29.5 million to Morgan Stanley & Co. to finance the project. The City originally intended to sell $31.8 million in bonds. However, due to Moody’s Investors Service upgrading the City of Shakopee bond rating in November, investors offered a $2.2 million premium for the bonds. This premium acts as additional revenue for the project and allowed the City to reduce its total bonding amount.

Background

In November 2014, the City Council approved a feasibility study and preliminary architectural work for expansion of athletic facilities at the Community Center and a preliminary look at the potential future use of the Central Family Center building.

Ballard*King and Associates, 292 Design Group and Springsted Inc. presented their Community Center Feasibility Study [PDF] during the March 31, 2015, City Council meeting. The study looked at market conditions, desired recreation amenities and financing options for expanding the Community Center. In addition, the study looked at several financing options, including referendum bonds, tax-abatement bonds, lease-revenue bonds, sales-tax referendum bonds, City fund balance, inter-fund loans and recreation facility revenue bonds.

Additional options considered: